Wilsom Farm
Wilsom Farm is a 4.01 MW solar farm in South East England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South East
- England
Key facts
- Installed capacity
- 4.01 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Greencoat Capital
- Region
- South East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- GU34 3BF
- Coordinates
- 51.1444, -0.9610
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Wilsom Farm compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.01 MW station would generate roughly 3.5 GWh of electricity in a year, similar to the annual use of about 1,300 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South East All run by Greencoat CapitalNearby generating sites
- Upper Farringdon Β· 6.18 MW solar farm3.6 km
- Upper Farm Β· 10 MW solar farm9.7 km
- Bishops Sutton Β· 12 MW solar farm14.9 km
- Hungerford Β· 4.47 MW solar farm16.1 km
- Hill End Farm Β· 2.84 MW solar farm21.4 km
- Berry Court Β· 3.92 MW solar farm23.1 km
- Overton Β· 3.75 MW solar farm25.1 km
- Lovedean Β· 4.54 MW solar farm26.3 km
Also operated by Greencoat Capital
Greencoat Capital operates 195 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Developer / operator
- Canadian solar
- Planning authority
- East Hampshire
- Planning reference
- 55465/001
- Application submitted
- 20 January 2015
- Permission granted
- 2 November 2015
- Construction started
- 21 December 2015
- Began operating
- 31 March 2016
- Capacity in planning record
- 11 MW
- Address
- Cakers Lane, East Worldham, Alton, Hampshire, Hampshire, GU34 3AB
- REPD reference
- 1515
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.