Shelswell
Shelswell is a 5.06 MW solar farm in South East England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South East
- England
Key facts
- Installed capacity
- 5.06 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Anesco
- Region
- South East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- OX27 8EH
- Coordinates
- 51.9740, -1.1160
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Shelswell compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5.06 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,640 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South East All run by AnescoNearby generating sites
- Turweston Β· 16.4 MW solar farm7.2 km
- Radstone Β· 5.22 MW solar farm9.2 km
- Bicester Β· 18.4 MW solar farm12.3 km
- New Stone House Β· 11.5 MW solar farm12.7 km
- Brook Farm Β· 8.91 MW solar farm13.9 km
- Culworth Β· 3.64 MW solar farm16.2 km
- Rowles Β· 12.8 MW solar farm16.3 km
- Mount Mill Β· 12 MW solar farm16.9 km
Also operated by Anesco
Anesco operates 136 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Shelswell Park Solar Farm
- Developer / operator
- Anesco
- Planning authority
- Cherwell
- Planning reference
- 11/00177/F
- Application submitted
- 7 February 2011
- Permission granted
- 20 May 2011
- Began operating
- 22 March 2013
- Capacity in planning record
- 5 MW
- Address
- Fringford, Oxfordshire, Oxfordshire
- REPD reference
- 1552
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.