Ratcliffe House Farm
Ratcliffe House Farm is a 3.5 MW solar farm in East Midlands England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- East Midlands
- England
Key facts
- Installed capacity
- 3.5 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Octopus Investments
- Region
- East Midlands
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- CV9 3LZ
- Coordinates
- 52.5946, -1.5079
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Ratcliffe House Farm compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 3.5 MW station would generate roughly 3.1 GWh of electricity in a year, similar to the annual use of about 1,140 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in East Midlands All run by Octopus InvestmentsNearby generating sites
- Magazine Β· 3.45 MW solar farm5.9 km
- Basin Bridge Β· 4.99 MW solar farm7.1 km
- Stables Β· 1.97 MW solar farm7.3 km
- Nailstone Β· 4.98 MW solar farm12.1 km
- Ibstock Β· 4.82 MW solar farm14.0 km
- Lindridge Β· 4.92 MW solar farm14.3 km
- Spring Lane Β· 0.96 MW solar farm15.2 km
- Tower Hayes Β· 5 MW solar farm15.7 km
Also operated by Octopus Investments
Octopus Investments operates 134 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Ld NW Of Ratcliffe House Farm
- Developer / operator
- Lightsource Renewable Energy
- Planning authority
- Hinckley and Bosworth
- Planning reference
- 15/00560/FUL
- Application submitted
- 19 May 2015
- Permission granted
- 17 August 2015
- Construction started
- 19 October 2015
- Began operating
- 21 December 2015
- Capacity in planning record
- 3.5 MW
- Address
- Ld NW Of Ratcliffe House Farm, Ratcliffe House Lane, Ratcliffe Culey, Atherstone, Leicestershire, CV9 3LZ
- REPD reference
- 5305
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.