πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
SOLAR Β· OPERATIONAL

Stables

Stables is a 1.97 MW solar farm in East Midlands England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • East Midlands
  • England
Project stageOperating
  1. PlanningOct 2012 (completed)
  2. ConsentedApr 2014 (completed)
  3. Construction (completed)
  4. OperatingAug 2014 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
1.97 MW
Status
Operational
Technology
Solar Β· PV
Operator
Greencoat Capital
Region
East Midlands
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
CV13 6EB
Coordinates
52.5703, -1.4078

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Stables compares

610th of 662largest solar farms in the UK register
89th of 95in East Midlands
0.03%of listed UK solar farms capacity
β‰ˆ 1.7 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 1.97 MW station would generate roughly 1.7 GWh of electricity in a year, similar to the annual use of about 640 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in East Midlands All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
The Stables
Developer / operator
Anesco
Planning authority
Hinckley and Bosworth
Planning reference
12/00873/FUL
Application submitted
29 October 2012
Permission granted
14 April 2014
Began operating
22 August 2014
Capacity in planning record
1.8 MW
Address
The Stables, Pine Close, Stoke Golding, Nuneaton, Leicestershire, Leicestershire, CV13 6EB
REPD reference
1510

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.