Spring Lane is a 0.96 MW solar farm in East Midlands England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • East Midlands
  • England
Project stageOperating
  1. PlanningJul 2015 (completed)
  2. ConsentedOct 2015 (completed)
  3. ConstructionAug 2016 (completed)
  4. OperatingNov 2016 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
0.96 MW
Status
Operational
Technology
Solar Β· PV
Operator
Anesco
Region
East Midlands
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
LE65 1WU
Coordinates
52.7279, -1.4589

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Spring Lane compares

647th of 662largest solar farms in the UK register
92nd of 95in East Midlands
0.02%of listed UK solar farms capacity
β‰ˆ 0.8 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 0.96 MW station would generate roughly 0.8 GWh of electricity in a year, similar to the annual use of about 310 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in East Midlands All run by Anesco

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Land at Hill Farm
Developer / operator
Hill Farm
Planning authority
North West Leicestershire
Planning reference
15/00719/FULM
Application submitted
23 July 2015
Permission granted
12 October 2015
Construction started
15 August 2016
Began operating
1 November 2016
Capacity in planning record
1.2 MW
Address
Hill Farm, Spring Lane, Packington, Ashby-De-La-Zouch, Leicestershire, LE65 1WU
REPD reference
5530

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.