Moss Thorn
Moss Thorn is a 4.97 MW solar farm in North West England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- North West
- England
Key facts
- Installed capacity
- 4.97 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Anesco
- Region
- North West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- CA11 0BY
- Coordinates
- 54.6678, -2.7983
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Moss Thorn compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.97 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,610 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in North West All run by AnescoNearby generating sites
- Wreay Β· 4.98 MW solar farm17.8 km
- Carlisle Estate Β· 5 MW solar farm19.9 km
- High Pow Β· 3.9 MW onshore wind farm28.5 km
- Great Orton Β· 3.96 MW onshore wind farm28.6 km
- Gedulah Β· 18.3 MW solar farm36.0 km
- Tallentire Wind Farm (GB) Β· 12 MW onshore wind farm36.3 km
- Westnewton (BEGL4) Β· 6.15 MW onshore wind farm37.3 km
- Lambrigg Β· 6.5 MW onshore wind farm38.3 km
Also operated by Anesco
Anesco operates 136 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Moss Thorn Farm
- Developer / operator
- TGC Renewables
- Planning authority
- Westmorland and Furness
- Planning reference
- 15/0459
- Application submitted
- 29 May 2015
- Permission granted
- 11 October 2016
- Construction started
- 14 November 2016
- Began operating
- 27 February 2017
- Capacity in planning record
- 5.8 MW
- Address
- Land near Moss Thorn Farm, Pallet Hill, Penrith, Cumbria
- REPD reference
- 6019
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.