SOLAR Β· OPERATIONAL

Wreay

Wreay is a 4.98 MW solar farm in North West England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • North West
  • England
Project stageOperating
  1. PlanningJul 2015 (completed)
  2. ConsentedAug 2016 (completed)
  3. ConstructionDec 2016 (completed)
  4. OperatingMar 2017 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.98 MW
Status
Operational
Technology
Solar Β· PV
Operator
Anesco
Region
North West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
CA4 0PY
Coordinates
54.8173, -2.8992

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Wreay compares

386th of 662largest solar farms in the UK register
13th of 23in North West
0.09%of listed UK solar farms capacity
β‰ˆ 4.4 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.98 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in North West All run by Anesco

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Land at Wreay
Developer / operator
Anesco
Planning authority
Westmorland and Furness
Planning reference
15/0653
Application submitted
31 July 2015
Permission granted
4 August 2016
Construction started
15 December 2016
Began operating
29 March 2017
Capacity in planning record
5 MW
Address
Land At Wreay, Calthwaite, Penrith, Carlisle, Cumbria, CA4 0PY
REPD reference
5525

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.