Milkwall Solar Farm
Milkwall Solar Farm is a 3.5 MW solar farm in South West England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South West
- England
Key facts
- Installed capacity
- 3.5 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Anesco
- Region
- South West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- GL16 8QD
- Coordinates
- 51.7817, -2.6154
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Milkwall Solar Farm compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 3.5 MW station would generate roughly 3.1 GWh of electricity in a year, similar to the annual use of about 1,140 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South West All run by AnescoNearby generating sites
- Coleford Pingry Solar Farm Β· 3.4 MW solar farm0.5 km
- Berkeley Nuclear Power Station Β· 276 MW nuclear power station12.7 km
- Oldbury Nuclear Power Station Β· 434 MW nuclear power station15.0 km
- Hill House Farm Β· 28.3 MW solar farm18.2 km
- Rhewl 2 Β· 3.07 MW solar farm18.2 km
- Rhewl 1 Β· 3.04 MW solar farm18.3 km
- Box Road Β· 1.9 MW solar farm18.5 km
- Upper Wick Β· 5 MW solar farm19.4 km
Also operated by Anesco
Anesco operates 136 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Pingry Farm - Phase 2
- Developer / operator
- Coleford Energy
- Planning authority
- Forest of Dean
- Planning reference
- P1418/12/FUL
- Application submitted
- 6 March 2013
- Permission granted
- 11 April 2013
- Construction started
- 1 January 2015
- Began operating
- 25 March 2015
- Capacity in planning record
- 3.4 MW
- Address
- Land At Pingry Farm, Pingry Lane, Milkwall, Coleford, Gloucestershire, GL16 8QD
- REPD reference
- 5230
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.