Lincoln Farm

Lincoln Farm is a 10.7 MW solar farm in East Midlands England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • East Midlands
  • England
Project stageOperating
  1. PlanningMar 2014 (completed)
  2. ConsentedOct 2014 (completed)
  3. ConstructionMay 2016 (completed)
  4. OperatingMar 2016 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
10.7 MW
Status
Operational
Technology
Solar Β· PV
Operator
Anesco
Region
East Midlands
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
PE24 5AT
Coordinates
53.1418, 0.2015

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Lincoln Farm compares

134th of 662largest solar farms in the UK register
26th of 95in East Midlands
0.19%of listed UK solar farms capacity
β‰ˆ 9.4 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 10.7 MW station would generate roughly 9.4 GWh of electricity in a year, similar to the annual use of about 3,470 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in East Midlands All run by Anesco

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
juwi Renewable Energies
Planning authority
East Lindsey
Planning reference
S/020/02242/13
Application submitted
7 March 2014
Permission granted
20 October 2014
Construction started
1 May 2016
Began operating
25 March 2016
Capacity in planning record
11.4 MW
Address
Lincoln Farm, Wainfleet Road, Irby In The Marsh, Skegness, Lincolnshire, PE24 5AT
REPD reference
1826

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.