Hyde Farm
Hyde Farm is a 4.94 MW solar farm in South East England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South East
- England
Key facts
- Installed capacity
- 4.94 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Anesco
- Region
- South East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- MK46 4DU
- Coordinates
- 52.1763, -0.7033
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Hyde Farm compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.94 MW station would generate roughly 4.3 GWh of electricity in a year, similar to the annual use of about 1,600 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South East All run by AnescoNearby generating sites
- Salcey Farm Β· 5.46 MW solar farm4.9 km
- Milton Keynes Β· 14 MW onshore wind farm5.0 km
- Bulls Head North Β· 5.51 MW solar farm7.7 km
- Airfield Poddington Β· 8.55 MW onshore wind farm9.3 km
- Littlewood Β· 5 MW solar farm9.5 km
- Littlewood Β· 13.7 MW solar farm9.5 km
- Roade Β· 7.2 MW onshore wind farm10.9 km
- UK Solar (Hartwell) LLP Β· 18.6 MW solar farm11.4 km
Also operated by Anesco
Anesco operates 136 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Developer / operator
- Conergy
- Planning authority
- Milton Keynes
- Planning reference
- 15/01791/FUL
- Application submitted
- 7 August 2015
- Permission granted
- 12 January 2016
- Construction started
- 16 December 2016
- Began operating
- 16 March 2017
- Capacity in planning record
- 5 MW
- Address
- Hyde Farm, Warrington Road, Olney, Buckinghamshire, MK46 4DU
- REPD reference
- 5685
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.