WIND Β· OPERATIONAL

Roade

Roade is a 7.2 MW onshore wind farm in East Midlands England, operated by EDF Energy. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • East Midlands
  • England

Key facts

Installed capacity
7.2 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
EDF Energy
Region
East Midlands
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
NN7 2EG
Coordinates
52.1617, -0.8617

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Roade compares

377th of 488largest wind farms in the UK register
27th of 34in East Midlands
0.02%of listed UK wind farms capacity
β‰ˆ 16 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 7.2 MW station would generate roughly 16 GWh of electricity in a year, similar to the annual use of about 6,070 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in East Midlands All run by EDF Energy

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
M1 Wind Farm
Developer / operator
Wind Prospect Developments
Planning authority
West Northamptonshire
Planning reference
S/2011/1421/MAF
Application submitted
8 November 2011
Permission granted
9 May 2013
Began operating
30 June 2014
Capacity in planning record
7.2 MW
Address
Land between Roade Courteenhall Hartwell and the M1, Northamptonshire
REPD reference
4399

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.