SOLAR Β· OPERATIONAL

Cotgrave

Cotgrave is a 4.98 MW solar farm in East Midlands England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • East Midlands
  • England
Project stageOperating
  1. PlanningJun 2014 (completed)
  2. ConsentedJan 2015 (completed)
  3. ConstructionMay 2015 (completed)
  4. OperatingJul 2015 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.98 MW
Status
Operational
Technology
Solar Β· PV
Operator
Anesco
Region
East Midlands
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
NG12 3GU
Coordinates
52.9180, -1.0500

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Cotgrave compares

386th of 662largest solar farms in the UK register
56th of 95in East Midlands
0.09%of listed UK solar farms capacity
β‰ˆ 4.4 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.98 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in East Midlands All run by Anesco

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Cotgrave solar farm
Developer / operator
Anesco
Planning authority
Rushcliffe
Planning reference
14/01221/FUL
Application submitted
23 June 2014
Permission granted
28 January 2015
Construction started
15 May 2015
Began operating
15 July 2015
Capacity in planning record
4.9 MW
Address
Blackberry Farm Main Road Cotgrave Nottinghamshire, Nottinghamshire
REPD reference
1843

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.