Cotgrave
Cotgrave is a 4.98 MW solar farm in East Midlands England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- East Midlands
- England
Key facts
- Installed capacity
- 4.98 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Anesco
- Region
- East Midlands
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- NG12 3GU
- Coordinates
- 52.9180, -1.0500
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Cotgrave compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.98 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in East Midlands All run by AnescoNearby generating sites
- Stragglethorpe Β· 5 MW solar farm0.8 km
- Radcliffe Β· 4.16 MW solar farm2.4 km
- Gedling Β· 5.74 MW solar farm8.3 km
- Dalby Solar Β· 6.88 MW solar farm12.9 km
- Wymeswold - Wide Lane Β· 4.28 MW solar farm12.9 km
- Wymeswold Β· 2.13 MW solar farm13.4 km
- Dalby Β· 7.29 MW onshore wind farm13.9 km
- Six Hills Β· 18.7 MW solar farm14.8 km
Also operated by Anesco
Anesco operates 136 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Cotgrave solar farm
- Developer / operator
- Anesco
- Planning authority
- Rushcliffe
- Planning reference
- 14/01221/FUL
- Application submitted
- 23 June 2014
- Permission granted
- 28 January 2015
- Construction started
- 15 May 2015
- Began operating
- 15 July 2015
- Capacity in planning record
- 4.9 MW
- Address
- Blackberry Farm Main Road Cotgrave Nottinghamshire, Nottinghamshire
- REPD reference
- 1843
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.