Radcliffe
Radcliffe is a 4.16 MW solar farm in East Midlands England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- East Midlands
- England
Key facts
- Installed capacity
- 4.16 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Anesco
- Region
- East Midlands
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- NG12 2LT
- Coordinates
- 52.9375, -1.0635
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Radcliffe compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.16 MW station would generate roughly 3.6 GWh of electricity in a year, similar to the annual use of about 1,350 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in East Midlands All run by AnescoNearby generating sites
- Stragglethorpe Β· 5 MW solar farm2.1 km
- Cotgrave Β· 4.98 MW solar farm2.4 km
- Gedling Β· 5.74 MW solar farm6.0 km
- Watnall Β· 10 MW solar farm14.4 km
- Wymeswold - Wide Lane Β· 4.28 MW solar farm15.1 km
- Ratcliffe-on-Soar Power Station Β· 2,116 MW coal-fired power station15.1 km
- Dalby Solar Β· 6.88 MW solar farm15.1 km
- Wymeswold Β· 2.13 MW solar farm15.2 km
Also operated by Anesco
Anesco operates 136 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Radcliffe Solar Farm
- Developer / operator
- Sirius Solar Building
- Planning authority
- Rushcliffe
- Planning reference
- 14/01228/FUL
- Application submitted
- 23 June 2014
- Permission granted
- 14 November 2014
- Construction started
- 13 April 2015
- Began operating
- 13 June 2015
- Capacity in planning record
- 4.2 MW
- Address
- Land South East Of Holme House Stragglethorpe Road Holme Pierrepont Nottinghamshire, Nottinghamshire
- REPD reference
- 2017
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.