SOLAR Β· OPERATIONAL

Ashton

Ashton is a 4.81 MW solar farm in South West England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South West
  • England
Project stageOperating
  1. PlanningJul 2015 (completed)
  2. ConsentedDec 2015 (completed)
  3. ConstructionDec 2016 (completed)
  4. OperatingMar 2017 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.81 MW
Status
Operational
Technology
Solar Β· PV
Operator
Anesco
Region
South West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
BA14 6DX
Coordinates
51.3222, -2.1596

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Ashton compares

460th of 662largest solar farms in the UK register
110th of 192in South West
0.09%of listed UK solar farms capacity
β‰ˆ 4.2 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.81 MW station would generate roughly 4.2 GWh of electricity in a year, similar to the annual use of about 1,560 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South West All run by Anesco

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Land north of Ashton Road
Developer / operator
Conergy
Planning authority
Wiltshire
Planning reference
15/07413/FUL
Application submitted
22 July 2015
Permission granted
22 December 2015
Construction started
24 December 2016
Began operating
24 March 2017
Capacity in planning record
4 MW
Address
Land north of, Ashton Road, Ashton Common, Steeple Ashton, Trowbridge, Wiltshire, Wiltshire, BA14 6DY
REPD reference
5498

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.