Home › Grid infrastructure › Connection queue

NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown2,255782.1 GW in total
In planning1,590scoping or awaiting consent
Consented or building265closest to connecting
Built400connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

2,255 projects · page 46 of 46
ProjectCapacityStageConnection siteFrom
Sellindge Grid Stability Services
Other · Sellindge Grid Services Limited
0 MWConsents Approved Sellindge 400kV Substation
National Grid (England & Wales)
Aug 2026
Spennymoor Greener Grid Park
Battery storage · Spennymoor Grid Solutions Limited
0 MWAwaiting Consents Spennymoor 400kV Substation
National Grid (England & Wales)
Oct 2027
Swansea Greener Grid Park - Connection 2
Other · Swansea Grid Solutions Limited
0 MWConsents Approved Swansea North 400kV Substation
National Grid (England & Wales)
Jul 2025
Thurso South Synchronous Compensation
Other · Thurso Grid Services Limited
0 MWBuilt Thurso GSP
SSEN Transmission (north Scotland)
Walpole Grid Services Facility
Other · Conrad (Walpole) Limited
0 MWConsents Approved Walpole 400kV Substation
National Grid (England & Wales)
Jul 2026
Page 46 of 46

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.