🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Home › Grid infrastructure › Connection queue

NESO TEC REGISTER · GREAT BRITAIN

Wind + storage projects in the connection queue

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown10613.6 GW in total
In planning97scoping or awaiting consent
Consented or building2closest to connecting
Built7connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

106 projects · page 3 of 3
ProjectCapacityStageConnection siteFrom
Melvich Wind Energy Hub (BEGA)
Wind + storage · Melvich Wind Energy Hub Limited
43 MWAwaiting Consents Dounreay 2 275/33kV GSP Substation
SSEN Transmission (north Scotland)
Oct 2033
Edinbane Windfarm
Wind + storage · Vattenfall Wind Power Ltd
41 MWBuilt Edinbane 132/33kV Substation
SSEN Transmission (north Scotland)
Craig Nab Wind Energy Hub
Wind + storage · Craig Nab Wind Energy Hub Limited
36 MWScoping Ladyburn 132kV Substation
SP Transmission (south Scotland)
Aug 2031
Hywind Wind Farm
Wind + storage · Hywind (Scotland) Limited
30 MWBuilt Peterhead Grange GSP
SSEN Transmission (north Scotland)
Brae WF
Wind + storage · Wind 2 Limited
20 MWScoping Linnmill GSP
SP Transmission (south Scotland)
Aug 2032
Enoch Hill 2 Wind Farm
Wind + storage · RWE Renewables UK Onshore Wind Limited
10 MWAwaiting Consents Enoch Hill 2 Wind Farm 33kV Substation
SP Transmission (south Scotland)
Apr 2027
Page 3 of 3

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.