NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue on the National Grid (England & Wales) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown968461.1 GW in total
In planning968scoping or awaiting consent
Consented or building149closest to connecting
Built212connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

968 projects · page 2 of 20
ProjectCapacityStageConnection siteFrom
Tarchon
Interconnector · Tarchon Energy Limited
1.4 GWScoping East Anglia Connection Node 400kV Substation
National Grid (England & Wales)
Oct 2030
Scira-Dudgeon Extension
Offshore wind · Sheringham Shoal And Dudgeon Extensions Projco Limited
1.4 GWScoping Norwich Main 400kV Substation
National Grid (England & Wales)
Oct 2034
NatPower Kinoulton Green Energy Park
Battery storage · Dalby Energy Limited
1.3 GWScoping West Anglia Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2034
Isle of Man Offshore Wind Farm
Offshore wind · Mooir Vannin Offshore Wind Farm Limited
1.3 GWScoping Imw01 Offshore 275/66Kv Offshore Substation
National Grid (England & Wales)
Sep 2037
Norfolk Boreas
Offshore wind · Norfolk Boreas Limited
1.3 GWScoping Necton 400kV Substation
National Grid (England & Wales)
Dec 2030
Immingham
Battery storage · Vpi Immingham LLP
1.3 GWScoping Humber Refinery 400kV Substation
National Grid (England & Wales)
Oct 2028
FAB Link Interconnector
Interconnector · FAB Link Limited
1.3 GWAwaiting Consents Exeter 400kV Substation
National Grid (England & Wales)
Sep 2032
Little Horsted Energy Park
Solar + storage · Elements Green Development Ltd
1.3 GWScoping Sussex and Romney Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Seneca
Interconnector · Frontier Power International Limited
1.3 GWScoping Mablethorpe 400kV Substation
National Grid (England & Wales)
Nov 2031
Cold Norton
Solar + storage · Bsr Applications Limited
1.3 GWScoping South Anglia Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2036
Ferrybridge D
Hydro and pumped storage · Keadby Generation Limited
1.2 GWScoping Ferrybridge C 275kV Substation
National Grid (England & Wales)
Oct 2030
Legacy Green Energy Centre
Battery storage · Legacy Green Energy Limited
1.2 GWAwaiting Consents Legacy 400kV Substation
National Grid (England & Wales)
Oct 2037
Rampion Extension Offshore Wind Farm
Offshore wind · Rampion Extension Development Limited
1.2 GWScoping Bolney 400kV Substation
National Grid (England & Wales)
Dec 2029
The Beacon
Solar + storage · Beacon Solar Limited
1.2 GWScoping West Country Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2037
Vicarage Drove BESS
Battery storage · UK Transition Power Holdings Limited
1.2 GWScoping Trent Valley South Connection Node A 400kV
National Grid (England & Wales)
Oct 2034
Awel Y Mor
Offshore wind · Awel Y Mor Offshore Wind Farm Limited
1.1 GWScoping Bodelwyddan 400kV Substation
National Grid (England & Wales)
Mar 2030
Five Estuaries Offshore Wind Farm
Offshore wind · Five Estuaries Offshore Wind Farm Limited
1.1 GWScoping Five Estuaries 220/66 kV Offshore Substation
National Grid (England & Wales)
Oct 2030
Bradwell Energy Park
Solar + storage · Low Carbon Solar Park 28 Limited
1.1 GWScoping Rayleigh 400kV Substation
National Grid (England & Wales)
Oct 2034
Project Cobalt
Interconnector · Getlink Projects 2 Limited
1.1 GWScoping East Kent Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2036
Butlers Wood Green Energy Centre
Solar + storage · Butlers Wood Ng Limited
1.0 GWAwaiting Consents Butlers Wood 400kV Substation
National Grid (England & Wales)
Oct 2031
Cilfynydd Green Energy Centre
Solar + storage · Cilfynydd Ng Limited
1.0 GWAwaiting Consents Cilfynydd 400kV Substation
National Grid (England & Wales)
Oct 2033
Drakelow Green Energy Centre
Solar + storage · Drakelow Ng Limited
1.0 GWAwaiting Consents Drakelow 400kV Substation
National Grid (England & Wales)
Oct 2029
East Claydon Green Energy Centre
Solar + storage · East Claydon Green Ng Limited
1.0 GWAwaiting Consents East Claydon 400kV Substation
National Grid (England & Wales)
Oct 2034
Enderby Green Energy Centre
Solar + storage · Enderby BESS Limited
1.0 GWAwaiting Consents Enderby 400kV Substation
National Grid (England & Wales)
Oct 2028
Feckenham Green Energy Centre
Solar + storage · Feckenham Green Ng Limited
1.0 GWScoping Feckenham 400kV Substation
National Grid (England & Wales)
Oct 2032
Hams Hall Green Energy Centre
Solar + storage · Hams Hall Ng Limited
1.0 GWScoping Hams Hall 400kV Substation
National Grid (England & Wales)
Oct 2032
Hawthorn Pit Green Energy Centre
Solar + storage · Hawthorn Pit Ng Limited
1.0 GWAwaiting Consents Hawthorn Pit 400kV Substation
National Grid (England & Wales)
Oct 2032
Mablethorpe Green Energy Centre
Solar + storage · Mablethorpe Ng Limited
1.0 GWAwaiting Consents Mablethorpe 400kV Substation
National Grid (England & Wales)
Oct 2033
Overton Green Energy Centre
Solar + storage · Overton Ng Limited
1.0 GWAwaiting Consents Overton 275kV
National Grid (England & Wales)
Oct 2035
Pentir Green Energy Centre
Solar + storage · Innova Renewables Limited
1.0 GWAwaiting Consents Pentir 400kV Substation
National Grid (England & Wales)
Oct 2037
Swansea North Green Energy Centre
Solar + storage · Swansea North Green Ng Limited
1.0 GWScoping Swansea North 400kV Substation
National Grid (England & Wales)
Oct 2033
Thorpe Marsh Green Energy Centre
Solar + storage · Thorpe Marsh Ng Ltd
1.0 GWAwaiting Consents Thorpe Marsh 400kV Substation
National Grid (England & Wales)
Aug 2032
Willington Green Energy Centre
Solar + storage · Willington Ng Limited
1.0 GWAwaiting Consents Willington 400kV Substation
National Grid (England & Wales)
Oct 2031
Cormoran Offshore Wind Farm
Offshore wind · South West Wind Holdco Limited
1.0 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Dec 2036
Mererid Offshore Wind Farm
Offshore wind · South West Wind Holdco Limited
1.0 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Dec 2036
Ossian 4 Offshore Wind Farm
Offshore wind · Ossian Offshore Wind Farm Limited
1.0 GWScoping Cousland 400kV
National Grid (England & Wales)
Oct 2033
Alcemi Bramford Battery Energy Storage Facility Phase 2
Battery storage · Alcemi Storage Developments 1 Limited
1.0 GWScoping South Anglia Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2034
Alverdiscott Farm
Solar + storage · Alverdiscott 10 Renewables Ltd
1.0 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Apr 2037
Amersham Main
Solar + storage · Amersham 10 Renewables Limited
1.0 GWScoping London North West Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
BF88 Oakley
Solar + storage · Bluefield Renewable Developments Limited
1.0 GWScoping Chiltern Connection Node C 400kV Substation
National Grid (England & Wales)
Nov 2038
Biggleswade
Solar + storage · Biggleswade 10 Renewables Limited
1.0 GWScoping Biggleswade 400kV Substation
National Grid (England & Wales)
Oct 2034
Biggleswade High Impact Green Energy Hub
Solar + storage · Telis Energy UK Limited
1.0 GWScoping Biggleswade 400kV Substation
National Grid (England & Wales)
Oct 2034
Braintree
Solar + storage · Braintree 10 Renewables Limited
1.0 GWScoping Braintree 400kV Substation
National Grid (England & Wales)
Oct 2034
Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH)
Solar + storage · Telis Energy UK Limited
1.0 GWScoping Leeds North Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2035
Bushbury
Solar · Bushbury 10 Renewables Limited
1.0 GWScoping Staffordshire Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Canterbury North
Solar + storage · Canterbury North 10 Renewables Limited
1.0 GWScoping East Kent Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2030
Celtic 2 Offshore Wind Farm
Offshore wind · RWE Offshore Wind
1.0 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Oct 2031
Celtic Sea Offshore Wind Farm (ESB)
Offshore wind · Esb Asset Development UK Limited
1.0 GWScoping Celtic Sea 275/66Kv Offshore Substation
National Grid (England & Wales)
Oct 2031
Coryton
Solar · Coryton 10 Renewables Limited
1.0 GWScoping South Anglia Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2034
Daventry High Impact Green Energy Hub (HIGEH) 1
Solar + storage · Telis Energy UK Limited
1.0 GWScoping Derbyshire Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Page 2 of 20

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.