United States βΊ Grid βΊ Interconnection queues βΊ California
OTHER Β· CAISOPalco
Palco is a 6.8 MW other request withdrawn in the CAISO interconnection queue, in Humboldt County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2005 (completed)
- Withdrawn / abandonedAug 2011 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 82
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Rio Dell Substation 60kV
- Location
- Humboldt County, California
- Technology
- Other: 6.8 MW
- Total requested
- 6.8 MW
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 14 September 2005
- Proposed online date
- January 2006
- Withdrawn
- August 2011
Location
Marker shows the centre of Humboldt County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in Humboldt County
- Humboldt Bay Power Plant Repowering ProjectGas Β· 146 MW Β· built
- Intrepid EnergyWind + storage Β· 1,887 MW Β· withdrawn
- Tempest GenerationWind + storage Β· 1,887 MW Β· withdrawn
- Wellhead Power HumboldtGas Β· 167 MW Β· withdrawn
- Tepona Off-Shore WindOffshore wind Β· 162 MW Β· withdrawn
- Capetown 3 HybridWind + storage Β· 158 MW Β· withdrawn
- Humboldt Energy Facility (Agile Energy)Gas Β· 147 MW Β· withdrawn
- Capetown HybridOnshore wind Β· 135 MW Β· withdrawn
- Capetown 2 HybridWind + storage Β· 106 MW Β· withdrawn
- Bear River Wind FarmOnshore wind Β· 100 MW Β· withdrawn
- Redwood House Wind Power PlantOnshore wind Β· 72.0 MW Β· withdrawn
- Bear River Wind Farm Q=117Onshore wind Β· 70.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem