Redwood House Wind Power Plant

Redwood House Wind Power Plant is a 72.0 MW onshore wind request withdrawn in the CAISO interconnection queue, in Humboldt County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2011 (completed)
  2. Withdrawn / abandonedMay 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
866
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Humboldt-Bridgeville 115 kV line
Location
Humboldt County, California
Technology
Wind: 72.0 MW
Total requested
72.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 November 2011
Proposed online date
October 2015
Withdrawn
May 2012

Location

Marker shows the centre of Humboldt County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Humboldt County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem