ONSHORE WIND · CAISO

Bear River Ridge Wind Farm

Bear River Ridge Wind Farm is a 50.0 MW onshore wind request withdrawn in the CAISO interconnection queue, in Humboldt County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2007 (completed)
  2. Withdrawn / abandonedJul 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
212
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Rio Dell Substation 60kV
Location
Humboldt County, California
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Study phase
In Progress
Queue status
Withdrawn
Entered queue
9 May 2007
Proposed online date
December 2013
Withdrawn
July 2012

Location

Marker shows the centre of Humboldt County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Humboldt County