Raspberry Solar 1

Raspberry Solar 1 is a 15.6 MW solar request withdrawn in the CAISO interconnection queue, in Contra Costa County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandonedNov 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2338
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
SOBRANTE-STANDARD OIL SW STA #1
Location
Contra Costa County, California
Technology
Solar: 15.6 MW
Total requested
15.6 MW
Service type
Energy only (ERIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Withdrawn
Entered queue
17 April 2023
Proposed online date
July 2027
Withdrawn
November 2025

Location

Marker shows the centre of Contra Costa County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Contra Costa County