🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Florida

BATTERY STORAGE · SOUTHEAST

Battery storage project 114, Hillsborough County

Battery storage project 114, Hillsborough County is a 20.0 MW battery storage request built and operating in the Southeast interconnection queue, in Hillsborough County, Florida, connecting to Tampa Electric Company.

Queue statusOperating
  1. PlanningQueued Oct 2024 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
114
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tampa Electric Company
Connection point (POI)
Gannon Substation, Hillsborough County, Florida
Location
Hillsborough County, Florida
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
Interconnection Agreement Executed
Queue status
Operational
Entered queue
22 October 2024
Proposed online date
December 2025

Location

Marker shows the centre of Hillsborough County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Hillsborough County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem