United States βΊ Grid βΊ Interconnection queues βΊ Texas
OTHER Β· ERCOTBRP Lopeno BESS
BRP Lopeno BESS is a 10.0 MW other request built and operating in the ERCOT interconnection queue, in Zapata County, Texas.
Request details
- Queue ID
- 22INR0580
- Grid region
- ERCOT (Texas)
- Location
- Zapata County, Texas
- Technology
- Other: 10.0 MW
- Total requested
- 10.0 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Came online
- February 2022
Location
Marker shows the centre of Zapata County; the queue data does not give exact sites.
Other requests in Zapata County
- Cascabel Wind 2Onshore wind Β· 198 MW Β· agreement signed
- Cascabel Wind 1Onshore wind Β· 198 MW Β· agreement signed
- Corralitos Wind 1Onshore wind Β· 196 MW Β· agreement signed
- Corralitos Wind 2Onshore wind Β· 195 MW Β· agreement signed
- Falcon BESSBattery storage Β· 517 MW Β· in study
- Freedom Falcon BESSBattery storage Β· 502 MW Β· in study
- Vaquero 1 WindOnshore wind Β· 400 MW Β· in study
- Tetris SolarSolar Β· 359 MW Β· in study
- Sierra Madre SolarSolar Β· 255 MW Β· in study
- Zelus BESSBattery storage Β· 201 MW Β· in study
- Falcon Zapata Storage 138Battery storage Β· 201 MW Β· in study
- Barrosos Creek Wind 3Onshore wind Β· 198 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem