United States › Grid › Interconnection queues › California
ONSHORE WIND · CAISOTransfer Ridge Wind
Transfer Ridge Wind is a 60.0 MW onshore wind request withdrawn in the CAISO interconnection queue, in Butte County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2013 (completed)
- Withdrawn / abandonedFeb 2014 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 976
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- TABLE MTN-RIO OSO 230 KV Line
- Location
- Butte County, California
- Technology
- Wind: 60.0 MW
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 April 2013
- Proposed online date
- December 2016
- Withdrawn
- February 2014
Location
Marker shows the centre of Butte County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Butte County
- Solar + storage project 2019-G1, Butte CountySolar + storage · 300 MW · in study
- Solar + storage project 2023-G4, Butte CountySolar + storage · 100 MW · in study
- Ameresco Butte County LandfillOther · 4.0 MW · built
- Bull RunSolar + storage · 457 MW · withdrawn
- Stageline Energy StorageBattery storage · 214 MW · withdrawn
- Bull Run 2 EsBattery storage · 205 MW · withdrawn
- Chickaree Hybrid SolarSolar + storage · 173 MW · withdrawn
- Trailways Energy StorageBattery storage · 102 MW · withdrawn
- Butte SolarSolar · 75.0 MW · withdrawn
- Panem SolarSolar · 20.9 MW · withdrawn
- Meridian & Munjar Solar ProjectSolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem