Meridian & Munjar Solar Project

Meridian & Munjar Solar Project is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Butte County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2010 (completed)
  2. Withdrawn / abandonedJan 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
657
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Glenn #3 60 kV
Location
Butte County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
12 November 2010
Proposed online date
March 2012
Withdrawn
January 2011

Location

Marker shows the centre of Butte County; the queue data does not give exact sites.