United States βΊ Grid βΊ Interconnection queues βΊ Maine
ONSHORE WIND Β· ISO-NEWind
Wind is a 104 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Aroostook County, Maine.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2014 (completed)
- Withdrawn / abandonedApr 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 460
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Pittsfield 345KV
- Location
- Aroostook County, Maine
- Technology
- Wind: 104 MW
- Total requested
- 104 MW
- Service type
- Energy only (ERIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 29 April 2014
- Proposed online date
- December 2020
- Withdrawn
- April 2018
Location
Marker shows the centre of Aroostook County; the queue data does not give exact sites.
Other requests in Aroostook County
- Oakfield II Wind - Keene RoadOnshore wind Β· 136 MW Β· built
- WindOnshore wind Β· 905 MW Β· withdrawn
- WindOnshore wind Β· 630 MW Β· withdrawn
- WindOnshore wind Β· 601 MW Β· withdrawn
- WindOnshore wind Β· 601 MW Β· withdrawn
- WindOnshore wind Β· 601 MW Β· withdrawn
- WindOnshore wind Β· 601 MW Β· withdrawn
- WindOnshore wind Β· 500 MW Β· withdrawn
- WindOnshore wind Β· 500 MW Β· withdrawn
- WindOnshore wind Β· 376 MW Β· withdrawn
- SolarSolar Β· 319 MW Β· withdrawn
- SolarSolar Β· 300 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem