United States β€Ί Grid β€Ί Interconnection queues β€Ί California

GAS Β· CAISO

Williams Energy Center

Williams Energy Center is a 200 MW gas request withdrawn in the CAISO interconnection queue, in Colusa County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2008 (completed)
  2. Withdrawn / abandonedJul 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
360
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Cortina Substation 230kV Bus
Location
Colusa County, California
Technology
Gas: 200 MW
Total requested
200 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 May 2008
Proposed online date
June 2012
Withdrawn
July 2008

Location

Marker shows the centre of Colusa County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Colusa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem