SOLAR + STORAGE · CAISOGreasewood Hybrid
Greasewood Hybrid is a 494 MW solar + storage request withdrawn in the CAISO interconnection queue, in Colusa County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2020 (completed)
- Withdrawn / abandonedJul 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1699
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Delevan-Vaca #3 230kV line
- Location
- Colusa County, California
- Technology
- Solar: 327 MW · Battery: 167 MW
- Total requested
- 494 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 15 April 2020
- Proposed online date
- December 2023
- Withdrawn
- July 2020
Location
Marker shows the centre of Colusa County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Colusa County
- Descendant Ranch 1Solar + storage · 1,024 MW · agreement signed
- JanusSolar + storage · 164 MW · agreement signed
- Saloon Energy StorageBattery storage · 150 MW · agreement signed
- CowboySolar + storage · 312 MW · in study
- Off Stream Water StorageBattery storage · 68.9 MW · in study
- CPV ColusaGas · 715 MW · built
- Descendant Ranch 2Solar + storage · 1,024 MW · withdrawn
- Ranchero SolarSolar + storage · 450 MW · withdrawn
- Beauchamp 2 SolarSolar + storage · 225 MW · withdrawn
- Williams Energy CenterGas · 200 MW · withdrawn
- Cowboy HybridSolar + storage · 156 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem