United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTBlackbird Solar
Blackbird Solar is a 152 MW solar request withdrawn in the ERCOT interconnection queue, in Mitchell County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2019 (completed)
- Withdrawn / abandonedSep 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 21INR0266
- Grid region
- ERCOT (Texas)
- Developer
- ABEI ENERGY&INFRASTRUCTURE LLC
- Connection point (POI)
- 1318 China Grove 138kV
- Location
- Mitchell County, Texas
- Technology
- Solar: 152 MW
- Total requested
- 152 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 11 March 2019
- Proposed online date
- February 2022
- Withdrawn
- September 2020
Location
Marker shows the centre of Mitchell County; the queue data does not give exact sites.
Other requests in Mitchell County
- Hackberry Creek SolarSolar Β· 176 MW Β· agreement signed
- Zeus Mitchell BESS IISolar + storage Β· 1,043 MW Β· in study
- Zeus Mitchell BESSSolar + storage Β· 1,043 MW Β· in study
- Zeus Spade WindWind + storage Β· 987 MW Β· in study
- Zeus Mitchell SolarSolar + storage Β· 805 MW Β· in study
- River Boat SolarSolar + storage Β· 502 MW Β· in study
- Zeus Spade BESSWind + storage Β· 446 MW Β· in study
- Rabbit Hollow Energy StorageBattery storage Β· 342 MW Β· in study
- River Boat Power Gas PlantGas Β· 334 MW Β· in study
- Prairie Power WindOnshore wind Β· 303 MW Β· in study
- River Boat StorageSolar + storage Β· 207 MW Β· in study
- Sunflower Valley StorageBattery storage Β· 206 MW Β· in study