Onshore wind project GI-1411, Brown County

Onshore wind project GI-1411, Brown County is a 99.0 MW onshore wind request withdrawn in the West interconnection queue, in Brown County, South Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2014 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-1411
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Connection point (POI)
Groton 115kV
Location
Brown County, South Dakota
Technology
Wind: 99.0 MW
Total requested
99.0 MW
Service type
Network resource (NRIS)
Study phase
IAP
Queue status
Withdrawn
Entered queue
14 August 2014
Proposed online date
December 2015

Location

Marker shows the centre of Brown County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Brown County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem