United States › Grid › Interconnection queues › California

GAS · CAISO

Pittsburg Power Plant - Ccu

Pittsburg Power Plant - Ccu is a 611 MW gas request withdrawn in the CAISO interconnection queue, in Contra Costa County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2008 (completed)
  2. Withdrawn / abandonedDec 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
322
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Pittsburg 230kV switchyard
Location
Contra Costa County, California
Technology
Gas: 611 MW
Total requested
611 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
18 March 2008
Proposed online date
September 2012
Withdrawn
December 2010

Location

Marker shows the centre of Contra Costa County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Contra Costa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem