Solar project SGI-PNM-2021-34, Otero County

Solar project SGI-PNM-2021-34, Otero County is a 10.0 MW solar request withdrawn in the West interconnection queue, in Otero County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2021 (completed)
  2. Withdrawn / abandonedNov 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
SGI-PNM-2021-34
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Tularosa Substation Distribution Feeder 13
Location
Otero County, New Mexico
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
20 July 2021
Proposed online date
August 2022
Withdrawn
November 2021

Location

Marker shows the centre of Otero County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Otero County