United States β€Ί Grid β€Ί Interconnection queues β€Ί California

GAS Β· CAISO

Wilbur Power CC

Wilbur Power CC is a 158 MW gas request withdrawn in the CAISO interconnection queue, in Contra Costa County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2005 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
63
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Contra Costa (230 kV)
Location
Contra Costa County, California
Technology
Gas: 158 MW
Total requested
158 MW
Study phase
In Progress
Queue status
Withdrawn
Entered queue
18 April 2005
Proposed online date
January 2008

Location

Marker shows the centre of Contra Costa County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Contra Costa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem