United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
BATTERY STORAGE Β· MISOBattery storage project J522, Mower County
Battery storage project J522, Mower County is a 20.0 MW battery storage request withdrawn in the MISO interconnection queue, in Mower County, Minnesota, connecting to ITC MIDWEST.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2015 (completed)
- Withdrawn / abandonedApr 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J522
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Adams substation at 69 kV
- Location
- Mower County, Minnesota
- Technology
- Battery: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 November 2015
- Proposed online date
- September 2019
- Withdrawn
- April 2019
Location
Marker shows the centre of Mower County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Mower County
- Onshore wind project J967, Mower CountyOnshore wind Β· 150 MW Β· under construction
- Solar project J1072, Mower CountySolar Β· 150 MW Β· under construction
- Solar project J523, Mower CountySolar Β· 50.0 MW Β· agreement signed
- Battery storage project J4078, Mower CountyBattery storage Β· 500 MW Β· in study
- Solar project J3903, Mower CountySolar Β· 185 MW Β· in study
- Solar project J2861, Mower CountySolar Β· 147 MW Β· in study
- Solar project J4057, Mower CountySolar Β· 127 MW Β· in study
- Onshore wind project G172, Mower CountyOnshore wind Β· 300 MW Β· built
- Onshore wind project G113, Mower CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project J278, Mower CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project G362, Mower CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project G330, Mower CountyOnshore wind Β· 19.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem