United States › Grid › Interconnection queues › California

ONSHORE WIND · CAISO

Carquinez Wind

Carquinez Wind is a 100 MW onshore wind request withdrawn in the CAISO interconnection queue, in Contra Costa County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2007 (completed)
  2. Withdrawn / abandonedJan 2009 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
177
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Bahia Moraga 230 kV Line
Location
Contra Costa County, California
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
28 February 2007
Proposed online date
December 2011
Withdrawn
January 2009

Location

Marker shows the centre of Contra Costa County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Contra Costa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem