πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

GAS Β· ERCOT

PES 2 Power Station

PES 2 Power Station is a 102 MW gas request built and operating in the ERCOT interconnection queue, in Harris County, Texas.

Queue statusOperating
  1. PlanningQueued Jul 2020 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingNov 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0371
Grid region
ERCOT (Texas)
Developer
HO CLARKE GENERATING LLC
Connection point (POI)
47150 H.O. Clarke 138kV
Location
Harris County, Texas
Technology
Gas: 102 MW
Total requested
102 MW
Study phase
IA
Queue status
Operational
Entered queue
23 July 2020
Proposed online date
November 2021
Came online
November 2021

Location

Marker shows the centre of Harris County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Harris County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem