πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OTHER Β· ERCOT

Mainland BESS

Mainland BESS is a 9.9 MW other request built and operating in the ERCOT interconnection queue, in Galveston County, Texas.

Queue statusOperating
  1. PlanningQueued Aug 2023 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0624
Grid region
ERCOT (Texas)
Developer
HEN INFRASTRUCTURE LLC 1
Connection point (POI)
Substation/BUS#/ERCOTBUS/ERCOTLOAD/DAC_x000D_ MAINLAND/38830/TNMAINLAND1/MAINLD_2/MAINLAND_DL1
Location
Galveston County, Texas
Technology
Other: 9.9 MW
Total requested
9.9 MW
Study phase
MRD Approved
Queue status
Operational
Entered queue
29 August 2023
Proposed online date
June 2024
Came online
June 2024

Location

Marker shows the centre of Galveston County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Galveston County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem