United States βΊ Grid βΊ Interconnection queues βΊ Texas
OTHER Β· ERCOTMainland BESS
Mainland BESS is a 9.9 MW other request built and operating in the ERCOT interconnection queue, in Galveston County, Texas.
Request details
- Queue ID
- 24INR0624
- Grid region
- ERCOT (Texas)
- Developer
- HEN INFRASTRUCTURE LLC 1
- Connection point (POI)
- Substation/BUS#/ERCOTBUS/ERCOTLOAD/DAC_x000D_ MAINLAND/38830/TNMAINLAND1/MAINLD_2/MAINLAND_DL1
- Location
- Galveston County, Texas
- Technology
- Other: 9.9 MW
- Total requested
- 9.9 MW
- Study phase
- MRD Approved
- Queue status
- Operational
- Entered queue
- 29 August 2023
- Proposed online date
- June 2024
- Came online
- June 2024
Location
Marker shows the centre of Galveston County; the queue data does not give exact sites.
Other requests in Galveston County
- Red Egret BESSBattery storage Β· 311 MW Β· agreement signed
- Shepard Energy StorageBattery storage Β· 257 MW Β· agreement signed
- Zeya BESSBattery storage Β· 255 MW Β· agreement signed
- Vertus Energy StorageBattery storage Β· 207 MW Β· agreement signed
- Southern Select Energy StorageBattery storage Β· 205 MW Β· agreement signed
- Wizard BESSBattery storage Β· 151 MW Β· agreement signed
- Air Products GCAGas Β· 14.0 MW Β· agreement signed
- Hidden Lakes BESSBattery storage Β· 9.9 MW Β· agreement signed
- Hecate Energy Jamaica WindOnshore wind Β· 1,029 MW Β· in study
- Hacienda StorageBattery storage Β· 202 MW Β· in study
- Kresge Land Battery StorageBattery storage Β· 200 MW Β· in study
- Valcrest BESSBattery storage Β· 154 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem