SOLAR · SOUTHEASTSolar project 195, Suwannee County
Solar project 195, Suwannee County is a 74.9 MW solar request built and operating in the Southeast interconnection queue, in Suwannee County, Florida, connecting to Duke Energy Florida.
Request details
- Queue ID
- 195
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Florida
- Developer
- Duke Energy Florida, LLC
- Connection point (POI)
- Suwannee River Plant Substation
- Location
- Suwannee County, Florida
- Technology
- Solar: 74.9 MW
- Total requested
- 74.9 MW
- Service type
- NRIS and ERIS
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 22 September 2017
- Proposed online date
- June 2024
- Came online
- June 2024
Location
Marker shows the centre of Suwannee County; the queue data does not give exact sites.
Other requests in Suwannee County
- Solar project 218, Suwannee CountySolar · 74.9 MW · in study
- Solar project FC100384, Suwannee CountySolar · 74.9 MW · in study
- Solar project 290, Suwannee CountySolar · 74.9 MW · in study
- Solar project FC100385, Suwannee CountySolar · 74.9 MW · in study
- Solar project 307, Suwannee CountySolar · 74.9 MW · suspended
- Solar project 305, Suwannee CountySolar · 74.9 MW · suspended
- Solar project 308, Suwannee CountySolar · 74.9 MW · suspended
- Solar project 210, Suwannee CountySolar · 74.9 MW · built
- Solar project 202Solar · 74.5 MW · built
- Battery storage project 380, Suwannee CountyBattery storage · 30.0 MW · built
- Battery storage project 318, Suwannee CountyBattery storage · 5.0 MW · built
- Gas project 112, Suwannee CountyGas · 950 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem