United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

ONSHORE WIND Β· MISO

Onshore wind project J3366, Sunflower County

Onshore wind project J3366, Sunflower County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Sunflower County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3366
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI, LLC.
Connection point (POI)
INDIANOLA 230/115 SUB - TILLATOBA 230.0kV
Location
Sunflower County, Mississippi
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
16 April 2024
Proposed online date
March 2028
Withdrawn
August 2025

Location

Marker shows the centre of Sunflower County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Other requests in Sunflower County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem