ONSHORE WIND Β· MISO

Onshore wind project G888, Benton County

Onshore wind project G888, Benton County is a 50.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Benton County, Indiana.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2007 (completed)
  2. Withdrawn / abandonedDec 2010 (project stopped here)
  3. ConsentedDec 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G888
Grid region
MISO (Midcontinent)
Connection point (POI)
Watseka - Goodland 138 kV
Location
Benton County, Indiana
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
16 October 2007
Agreement signed
28 December 2010
Proposed online date
December 2010
Withdrawn
December 2010

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.