BATTERY STORAGE · ERCOT

Houston BESS

Houston BESS is a 228 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Harris County, Texas.

Queue statusIn planning
  1. PlanningQueued Apr 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0420
Grid region
ERCOT (Texas)
Developer
SMT Houston
Connection point (POI)
Tap 138 kV LAUDER (#46002) - RITTENHOUSE (#46282) ckt 95
Location
Harris County, Texas
Technology
Battery: 228 MW
Total requested
228 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
7 April 2023
Proposed online date
December 2026

Location

Marker shows the centre of Harris County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Harris County