🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

High Plains Storage

High Plains Storage is a 158 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Harris County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0419
Grid region
ERCOT (Texas)
Developer
ROBP Holdings, LLC
Connection point (POI)
45880 Hockley 138kV
Location
Harris County, Texas
Technology
Battery: 158 MW
Total requested
158 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
2 September 2022
Proposed online date
May 2028

Location

Marker shows the centre of Harris County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Harris County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem