Other projects with signed interconnection agreements in the USA

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown275,506 MW
Active in queue74.4 GW328 requests
Agreement signed5,506 MW27 requests
Withdrawn1,273328.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

27 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Potentia-Viridi
Other
1,225 MWAgreement signed San Joaquin, CACAISO Apr 2020target 2028
Other project J1490, Randolph County
Other
1,000 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Willow Rock Energy Storage
Other
620 MWAgreement signed Kern, CACAISO Apr 2020target 2030
Other project Company KR, White Pine County
Other
600 MWAgreement signed White Pine, NVWest Sep 2020target 2028
Other project J1488, Randolph County
Other
500 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Other project 590, Elmore County
Other Β· Appaloosa Wind And Solar LLC
330 MWAgreement signed Elmore, IDWest Dec 2020target 2027
Other project CLPT G17, Laramie County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Laramie, WYWest Apr 2022target 2025
Other project CLPT G16, Platte County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Platte, WYWest Apr 2022target 2025
Surplus; Polaris Solar
Other
100 MWAgreement signed Gratiot, MIMISO Apr 2022target 2023
Surplus; Pine River Solar
Other
80.0 MWAgreement signed Gratiot, MIMISO Apr 2022target 2023
Other project 66, Stevens County
Other
71.0 MWAgreement signed Stevens, WAWest Jul 2018target 2026
Other project Q66, Stevens County
Other
71.0 MWAgreement signed Stevens, WAWest target 2026
Bottle Rock Power
Other
56.9 MWAgreement signed Lake, CACAISO Sep 20052007
Surplus; J1369
Other
50.0 MWAgreement signed Dubois, INMISO May 2022target 2022
Mea Nug
Other
50.0 MWAgreement signed Monongalia, WVPJM Sep 2020target 2028
Other project 70, Polk County
Other
48.0 MWAgreement signed Polk, FLSoutheast May 2020target 2021
Other project GEN-2024-GR4, Cherokee County
Other
27.1 MWAgreement signed Cherokee, KSSPP Jul 2024target 2026
Other project GEN-2023-SR1, Brown County
Other
21.9 MWAgreement signed Brown, NESPP Dec 20222024
Olney AGR1
Other Β· HEN INFRASTRUCTURE, LLC 1
10.0 MWAgreement signed Young, TXERCOT target 2026
Saddleback AGR1
Other Β· HEN INFRASTRUCTURE, LLC 1
10.0 MWAgreement signed Reeves, TXERCOT target 2026
Coyote Springs AGR1
Other Β· HEN INFRASTRUCTURE, LLC 1
10.0 MWAgreement signed Reeves, TXERCOT target 2026
Other project J963, Cedar County
Other
9.0 MWAgreement signed Cedar, IAMISO Mar 2018target 2017
Battery addition
Other
6.7 MWAgreement signed Franklin, MAISO-NE Aug 2021target 2027
Other project G177, Lyon County
Other
5.0 MWAgreement signed Lyon, MNMISO Mar 2002target 2004
Other project J953, Johnson County
Other
2.0 MWAgreement signed Johnson, IAMISO Mar 2018target 2006
Other project Company MN, Lyon County
Other
1.3 MWAgreement signed Lyon, NVWest Dec 2021target 2022
Other project J258, Stearns County
Other
1.0 MWAgreement signed Stearns, MNMISO Oct 2012target 2013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)