United States โ€บ Grid โ€บ Interconnection queues โ€บ Wyoming

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Wyoming

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown26962.1 GW
Active in queue18.7 GW80 requests
Agreement signed5,211 MW26 requests
Withdrawn26962.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

269 requests ยท page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Pathfinder Renewable Wind Energy
Onshore wind
3,000 MWWithdrawn / abandoned Platte, WYCAISO Mar 2011target 2020
Onshore wind project 177, Carbon County
Onshore wind
1,500 MWWithdrawn / abandoned Carbon, WYWest Dec 2007target 2014
Other project G265, Campbell County
Other
1,420 MWWithdrawn / abandoned Campbell, WYMISO Nov 2002target 2004
Onshore wind project 137, Converse County
Onshore wind
1,000 MWWithdrawn / abandoned Converse, WYWest May 2007target 2013
Solar project C3-052, Carbon County
Solar
1,000 MWWithdrawn / abandoned Carbon, WYWest May 2023target 2026
Battery storage project C1-25, Carbon County
Battery storage
900 MWWithdrawn / abandoned Carbon, WYWest May 2021target 2028
Battery storage project C3-013, Carbon County
Battery storage
900 MWWithdrawn / abandoned Carbon, WYWest Apr 2023target 2029
Battery storage project 1174, Carbon County
Battery storage
750 MWWithdrawn / abandoned Carbon, WYWest Oct 2019target 2026
Onshore wind project 1153, Carbon County
Onshore wind
665 MWWithdrawn / abandoned Carbon, WYWest Aug 2019target 2023
Onshore wind project 920, Albany County
Onshore wind
630 MWWithdrawn / abandoned Albany, WYWest Aug 2017target 2020
Onshore wind project 1173, Carbon County
Onshore wind
625 MWWithdrawn / abandoned Carbon, WYWest Oct 2019target 2023
Wind + storage project C3-024, Carbon County
Wind + storage
600 MWWithdrawn / abandoned Carbon, WYWest May 2023target 2027
Onshore wind project C2-46, Laramie County
Onshore wind
600 MWWithdrawn / abandoned Laramie, WYWest Apr 2022target 2025
Onshore wind project C2-43, Sweetwater County
Onshore wind
600 MWWithdrawn / abandoned Sweetwater, WYWest Apr 2022target 2025
Onshore wind project 927, Platte County
Onshore wind
600 MWWithdrawn / abandoned Platte, WYWest Aug 2017target 2020
Onshore wind project C1-48, Sweetwater County
Onshore wind
600 MWWithdrawn / abandoned Sweetwater, WYWest May 2021target 2025
Wind + storage project C3-025, Carbon County
Wind + storage
600 MWWithdrawn / abandoned Carbon, WYWest May 2023target 2027
Onshore wind project GI-2008-31, Laramie County
Onshore wind
600 MWWithdrawn / abandoned Laramie, WYWest Dec 2008target 2012
Onshore wind project C2-104, Lincoln County
Onshore wind
600 MWWithdrawn / abandoned Lincoln, WYWest May 2022target 2025
Onshore wind project 1154, Carbon County
Onshore wind
590 MWWithdrawn / abandoned Carbon, WYWest Aug 2019target 2023
Onshore wind project 940, Carbon County
Onshore wind
576 MWWithdrawn / abandoned Carbon, WYWest Aug 2017target 2020
Onshore wind project C2-34, Carbon County
Onshore wind
506 MWWithdrawn / abandoned Carbon, WYWest Apr 2022target 2024
Onshore wind project 1016, Carbon County
Onshore wind
502 MWWithdrawn / abandoned Carbon, WYWest Mar 2018target 2020
Onshore wind project 1015, Carbon County
Onshore wind
502 MWWithdrawn / abandoned Carbon, WYWest Mar 2018target 2020
Onshore wind project C2-108, Sweetwater County
Onshore wind
500 MWWithdrawn / abandoned Sweetwater, WYWest May 2022target 2025
Onshore wind project 135, Converse County
Onshore wind ยท Clipper Windpower Development Company, Inc
500 MWWithdrawn / abandoned Converse, WYWest May 2007target 2011
Gas project 50, Converse County
Gas
500 MWWithdrawn / abandoned Converse, WYWest Jan 2005target 2006
Onshore wind project C2-107, Sweetwater County
Onshore wind
500 MWWithdrawn / abandoned Sweetwater, WYWest May 2022target 2025
Onshore wind project C3-015, Sweetwater County
Onshore wind
500 MWWithdrawn / abandoned Sweetwater, WYWest Apr 2023target 2025
Battery storage project C2-25, Lincoln County
Battery storage ยท PacifiCorp
500 MWWithdrawn / abandoned Lincoln, WYWest Apr 2022target 2028
Battery storage project C2-17, Converse County
Battery storage ยท PacifiCorp
500 MWWithdrawn / abandoned Converse, WYWest Apr 2022target 2028
Battery storage project C3-068, Lincoln County
Battery storage ยท PacifiCorp
500 MWWithdrawn / abandoned Lincoln, WYWest May 2023target 2030
Onshore wind project 136, Converse County
Onshore wind ยท Clipper Windpower Development Company, Inc
500 MWWithdrawn / abandoned Converse, WYWest May 2007target 2012
Onshore wind project 872, Carbon County
Onshore wind
500 MWWithdrawn / abandoned Carbon, WYWest May 2017target 2020
Battery storage project C2-23, Converse County
Battery storage ยท PacifiCorp
500 MWWithdrawn / abandoned Converse, WYWest Apr 2022target 2028
Battery storage project C3-066, Converse County
Battery storage ยท PacifiCorp
500 MWWithdrawn / abandoned Converse, WYWest May 2023target 2030
Onshore wind project PIS004, Carbon County
Onshore wind
500 MWWithdrawn / abandoned Carbon, WYWest Apr 2022target 2025
Onshore wind project C3-016, Sweetwater County
Onshore wind
500 MWWithdrawn / abandoned Sweetwater, WYWest Apr 2023target 2025
Onshore wind project 191, Carbon County
Onshore wind
500 MWWithdrawn / abandoned Carbon, WYWest Jan 2008
Onshore wind project 1155, Carbon County
Onshore wind
470 MWWithdrawn / abandoned Carbon, WYWest Aug 2019target 2023
Onshore wind project C3-185, Carbon County
Onshore wind
450 MWWithdrawn / abandoned Carbon, WYWest May 2023target 2028
Gas project 134, Carbon County
Gas ยท Clipper Windpower Development Company, Inc.
430 MWWithdrawn / abandoned Carbon, WYWest May 2007target 2010
Onshore wind project 295, Carbon County
Onshore wind
403 MWWithdrawn / abandoned Carbon, WYWest Oct 2009target 2014
Onshore wind project 298, Albany County
Onshore wind
400 MWWithdrawn / abandoned Albany, WYWest Oct 2009target 2011
Onshore wind project 931, Platte County
Onshore wind
400 MWWithdrawn / abandoned Platte, WYWest Aug 2017target 2020
Onshore wind project 932, Platte County
Onshore wind
400 MWWithdrawn / abandoned Platte, WYWest Aug 2017target 2020
Onshore wind project C4-085, Carbon County
Onshore wind
400 MWWithdrawn / abandoned Carbon, WYWest May 2024target 2029
Onshore wind project 930, Platte County
Onshore wind
400 MWWithdrawn / abandoned Platte, WYWest Aug 2017target 2020
Onshore wind project 1183, Carbon County
Onshore wind
400 MWWithdrawn / abandoned Carbon, WYWest Oct 2019target 2024
Onshore wind project 1156, Carbon County
Onshore wind
380 MWWithdrawn / abandoned Carbon, WYWest Aug 2019target 2023
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)