Onshore wind project 295, Carbon County

Onshore wind project 295, Carbon County is a 403 MW onshore wind request withdrawn in the West interconnection queue, in Carbon County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2009 (completed)
  2. Withdrawn / abandonedOct 2013 (project stopped here)
  3. ConsentedMar 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
295
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Bus at Aeolus Basin substation
Location
Carbon County, Wyoming
Technology
Wind: 403 MW
Total requested
403 MW
Service type
Network resource (NRIS)
Study phase
IA signed 3/17/11, IA Terminated 10/3/2013
Queue status
Withdrawn
Entered queue
1 October 2009
Agreement signed
17 March 2011
Proposed online date
December 2014
Withdrawn
October 2013

Location

Marker shows the centre of Carbon County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Carbon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem