πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Wyoming

ONSHORE WIND Β· WEST

Onshore wind project GI-2008-31, Laramie County

Onshore wind project GI-2008-31, Laramie County is a 600 MW onshore wind request withdrawn in the West interconnection queue, in Laramie County, Wyoming, connecting to Public Service Company Of Colorado.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2008 (completed)
  2. Withdrawn / abandonedNov 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-2008-31
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Ault Substation
Location
Laramie County, Wyoming
Technology
Wind: 600 MW
Total requested
600 MW
Service type
NRIS and ERIS
Study phase
Feasibility Study underway Request Withdrawn 11/2/10
Queue status
Withdrawn
Entered queue
18 December 2008
Proposed online date
January 2012
Withdrawn
November 2010

Location

Marker shows the centre of Laramie County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Laramie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem