United States โ€บ Grid โ€บ Interconnection queues โ€บ Washington

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Washington (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6323.0 GW
Active in queue23.0 GW63 requests
Agreement signed500 MW4 requests
Withdrawn4515.6 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

63 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Other project G1025, Douglas County
Other
1,274 MWIn study Douglas, WAWest Nov 2023target 2029
Nuclear project G0998, Benton County
Nuclear
1,120 MWIn study Benton, WAWest Nov 2023target 2030
Battery storage project G0914, Douglas County
Battery storage
1,000 MWIn study Douglas, WAWest Jul 2023target 2028
Solar + storage project G1040, Benton County
Solar + storage
800 MWIn study Benton, WAWest Nov 2023target 2030
Solar + storage project G0932, Benton County
Solar + storage
800 MWIn study Benton, WAWest Sep 2023target 2029
Solar + storage project G1037, Benton County
Solar + storage
800 MWIn study Benton, WAWest Nov 2023target 2030
Solar + storage project G1039, Benton County
Solar + storage
800 MWIn study Benton, WAWest Nov 2023target 2030
Solar + storage project G0920, Benton County
Solar + storage
800 MWIn study Benton, WAWest Aug 2023target 2027
Solar + storage project G0933, Benton County
Solar + storage
800 MWIn study Benton, WAWest Sep 2023target 2029
Solar + storage project G1038, Benton County
Solar + storage
800 MWIn study Benton, WAWest Nov 2023target 2030
Wind + storage project G0921, Thurston County
Wind + storage
718 MWIn study Thurston, WAWest Sep 2023target 2030
Solar + storage project G0853, Douglas County
Solar + storage
600 MWIn study Douglas, WAWest Mar 2023target 2027
Wind + storage project G1007, Lewis County
Wind + storage
600 MWIn study Lewis, WAWest Nov 2023target 2030
Onshore wind project G0953, Lincoln County
Onshore wind
600 MWIn study Lincoln, WAWest Oct 2023target 2026
Solar + storage project G0840, Douglas County
Solar + storage
600 MWIn study Douglas, WAWest Feb 2023target 2027
Solar project G1032, Grant County
Solar
500 MWIn study Grant, WAWest Nov 2023target 2028
Battery storage project G0915, Douglas County
Battery storage
500 MWIn study Douglas, WAWest Jul 2023target 2028
Battery storage project G0916, Douglas County
Battery storage
500 MWIn study Douglas, WAWest Jul 2023target 2028
Solar project G1015, Benton County
Solar
500 MWIn study Benton, WAWest Nov 2023target 2029
Solar + storage project G0844, Klickitat County
Solar + storage
420 MWIn study Klickitat, WAWest Feb 2023target 2026
Solar project G1035, Douglas County
Solar
400 MWIn study Douglas, WAWest Nov 2023target 2028
Solar + storage project G0979, Klickitat County
Solar + storage
400 MWIn study Klickitat, WAWest Nov 2023target 2029
Solar project G1016, Klickitat County
Solar
400 MWIn study Klickitat, WAWest Nov 2023target 2029
Onshore wind project G0955, Lincoln County
Onshore wind
350 MWIn study Lincoln, WAWest Oct 2023target 2026
Onshore wind project G0954, Lincoln County
Onshore wind
350 MWIn study Lincoln, WAWest Oct 2023target 2026
Onshore wind project G0872, Garfield County
Onshore wind
300 MWIn study Garfield, WAWest Jun 2023target 2028
Other project G0924, Walla Walla County
Other
300 MWIn study Walla Walla, WAWest Sep 2023target 2027
Other project G0925, Walla Walla County
Other
300 MWIn study Walla Walla, WAWest Sep 2023target 2027
Onshore wind project G0973, Mason County
Onshore wind
300 MWIn study Mason, WAWest Oct 2023target 2029
Solar + storage project 9, Grant County
Solar + storage
300 MWIn study Grant, WAWest Sep 2023
Other project G0923, Walla Walla County
Other
300 MWIn study Walla Walla, WAWest Sep 2023target 2027
Solar + storage project G1047, Grant County
Solar + storage
300 MWIn study Grant, WAWest Nov 2023target 2026
Solar + storage project G1043, Grant County
Solar + storage
300 MWIn study Grant, WAWest Nov 2023target 2026
Solar + storage project 10, Grant County
Solar + storage
300 MWIn study Grant, WAWest Sep 2023
Solar + storage project G1048, Mason County
Solar + storage
300 MWIn study Mason, WAWest Nov 2023target 2027
Gas project G1008, Clark County
Gas
286 MWIn study Clark, WAWest Nov 2023target 2024
Nuclear project G0919, Benton County
Nuclear
270 MWIn study Benton, WAWest Aug 2023target 2031
Battery storage project G1014, King County
Battery storage
250 MWIn study King, WAWest Nov 2023target 2029
Solar project G1031, Klickitat County
Solar
250 MWIn study Klickitat, WAWest Nov 2023target 2028
Solar project G0935, Walla Walla County
Solar
225 MWIn study Walla Walla, WAWest Sep 2023target 2027
Solar + storage project G0985, Lincoln County
Solar + storage
225 MWIn study Lincoln, WAWest Nov 2023target 2027
Onshore wind project CS23-06, Whitman County
Onshore wind
221 MWAgreement signed Whitman, WAWest Apr 2023target 2028
Battery storage project CS23-12, Franklin County
Battery storage
199 MWAgreement signed Franklin, WAWest May 2023target 2029
Solar + storage project G1029, Benton County
Solar + storage
188 MWIn study Benton, WAWest Nov 2023target 2027
Solar + storage project G0843, Klickitat County
Solar + storage
180 MWIn study Klickitat, WAWest Feb 2023target 2026
Solar project G0847, Columbia County
Solar
150 MWIn study Columbia, WAWest Feb 2023target 2024
Solar project G1001, Grant County
Solar
150 MWIn study Grant, WAWest Nov 2023target 2029
Onshore wind project G0936, Klickitat County
Onshore wind
150 MWIn study Klickitat, WAWest Sep 2023target 2025
Onshore wind project G0992, Skagit County
Onshore wind
131 MWIn study Skagit, WAWest Nov 2023target 2028
Battery storage project 139, King County
Battery storage
130 MWIn study King, WAWest Dec 2023target 2028
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)