United States βΊ Grid βΊ Interconnection queues βΊ Washington
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Washington (2019 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project G0624, Garfield County Solar |
1,250 MW | Withdrawn / abandoned |
| Solar project G0614, Klickitat County Solar |
600 MW | Withdrawn / abandoned |
| Onshore wind project G0611, Klickitat County Onshore wind |
313 MW | Withdrawn / abandoned |
| Solar project G0632, Grant County Solar |
300 MW | Withdrawn / abandoned |
| Solar project 77, Grant County Solar |
300 MW | Withdrawn / abandoned |
| Solar project 78, Klickitat County Solar |
250 MW | Withdrawn / abandoned |
| Solar project 75, Douglas County Solar |
250 MW | Withdrawn / abandoned |
| Solar + storage project TCS-08, Franklin County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project 74, Douglas County Solar + storage |
160 MW | Withdrawn / abandoned |
| Solar project G0628, Kittitas County Solar |
125 MW | Withdrawn / abandoned |
| Solar project G0629, Benton County Solar |
100 MW | Withdrawn / abandoned |
| Solar + storage project TCS-09, Spokane County Solar + storage |
100 MW | Withdrawn / abandoned |
| Battery storage project 76, King County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project 98, Grant County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project G0634, Kittitas County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project G0612, Klickitat County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project G0627, Klickitat County Solar |
45.0 MW | Withdrawn / abandoned |
| Solar + storage project TCS-10, Lincoln County Solar + storage |
40.0 MW | Withdrawn / abandoned |
| Solar project 86, Lincoln County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project 1169, Yakima County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project 1148, Walla Walla County Solar |
5.0 MW | Withdrawn / abandoned |
| Battery storage project TCS-56, Yakima County Battery storage |
5.0 MW | Withdrawn / abandoned |
| Solar project 93, Adams County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project 91, Adams County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project 88, Adams County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project 89, Adams County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project 90, Adams County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project 92, Adams County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project 87, Lincoln County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project TCS-07, Adams County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project 94, Adams County Solar |
5.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)