United States βΊ Grid βΊ Interconnection queues βΊ Virginia
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Virginia (2018 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Blackwater Solar Solar |
800 MW | Agreement signed |
| Blue Ridge Solar Solar |
150 MW | Agreement signed |
| Riverstone Solar Solar |
150 MW | Agreement signed |
| Maroon Solar Solar |
149 MW | Paused / redesign |
| CC Solar I Solar |
120 MW | Paused / redesign |
| New Road Storage Battery storage |
120 MW | Agreement signed |
| Chester Solar Solar |
120 MW | Agreement signed |
| Blue Jay Solar Solar |
100 MW | Paused / redesign |
| Bakers Pond Solar Solar |
100 MW | Paused / redesign |
| Waller Solar I Solar |
86.0 MW | Agreement signed |
| Knoxville Solar Solar |
51.0 MW | Agreement signed |
| Sunridge Solar Solar |
50.0 MW | Agreement signed |
| Ho-Fel Solar Solar |
40.0 MW | Paused / redesign |
| Walnut Solar I Solar |
20.0 MW | Agreement signed |
| Winterpock I Solar |
20.0 MW | Agreement signed |
| Walnut Solar I Solar |
20.0 MW | Agreement signed |
| Walnut Solar I Solar |
20.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)