๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues โ€บ Virginia

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Virginia (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown617,607 MW
Active in queue6,737 MW37 requests
Agreement signed3,049 MW27 requests
Withdrawn617,607 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

61 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore wind project AE2-124, City Of Virginia Beach County
Offshore wind ยท Avangrid Renewables, LLC
800 MWWithdrawn / abandoned City Of Virginia Beach, VAPJM Feb 2019target 2029
Offshore wind project AE2-122, City Of Virginia Beach County
Offshore wind
800 MWWithdrawn / abandoned City Of Virginia Beach, VAPJM Feb 2019target 2025
Offshore wind project AE2-123, City Of Virginia Beach County
Offshore wind ยท Avangrid Renewables, LLC
800 MWWithdrawn / abandoned City Of Virginia Beach, VAPJM Feb 2019target 2027
Solar project AE2-311, Sussex County
Solar
400 MWWithdrawn / abandoned Sussex, VAPJM Mar 2019target 2021
Solar project AE2-313, Dinwiddie County
Solar ยท RWE Solar Development, LLC
314 MWWithdrawn / abandoned Dinwiddie, VAPJM Mar 2019target 2022
Solar project AF1-310, Halifax County
Solar
300 MWWithdrawn / abandoned Halifax, VAPJM Sep 2019target 2022
Solar project AE2-031, Sussex County
Solar
290 MWWithdrawn / abandoned Sussex, VAPJM Jan 2019target 2021
Solar project AF1-329, Charles City County
Solar
250 MWWithdrawn / abandoned Charles City, VAPJM Sep 2019target 2021
Gas project AF2-053, Charles City County
Gas
200 MWWithdrawn / abandoned Charles City, VAPJM Dec 2019target 2024
Solar + storage project AE2-260, Greensville County
Solar + storage
200 MWWithdrawn / abandoned Greensville, VAPJM Mar 2019target 2020
Battery storage project AF1-265, Hanover County
Battery storage
150 MWWithdrawn / abandoned Hanover, VAPJM Sep 2019target 2022
Solar + storage project AF1-201, Gloucester County
Solar + storage ยท TGE Virginia 195, LLC
150 MWWithdrawn / abandoned Gloucester, VAPJM Sep 2019target 2021
Solar + storage project AE2-270, Surry County
Solar + storage ยท Violet Wood Solar LLC
150 MWWithdrawn / abandoned Surry, VAPJM Mar 2019target 2021
Solar project AE2-287, Brunswick County
Solar
130 MWWithdrawn / abandoned Brunswick, VAPJM Mar 2019target 2022
Solar + storage project AF1-293, Fluvanna County
Solar + storage ยท Kidds Store, LLC
128 MWWithdrawn / abandoned Fluvanna, VAPJM Sep 2019target 2022
Solar project AE2-292, Campbell County
Solar ยท Eno Solar, LLC
127 MWWithdrawn / abandoned Campbell, VAPJM Mar 2019target 2021
Solar project AE2-280, Montgomery County
Solar
127 MWWithdrawn / abandoned Montgomery, VAPJM Mar 2019target 2022
Solar project AF1-301, Louisa County
Solar ยท Invenergy Solar Project Development LLC
117 MWWithdrawn / abandoned Louisa, VAPJM Sep 2019target 2022
Solar project AE2-157, Sussex County
Solar
100 MWWithdrawn / abandoned Sussex, VAPJM Mar 2019target 2021
Solar project AE2-328, Accomack County
Solar
100 MWWithdrawn / abandoned Accomack, VAPJM Mar 2019target 2022
Solar project AF1-246, Charlotte County
Solar
100 MWWithdrawn / abandoned Charlotte, VAPJM Sep 2019target 2022
Solar + storage project AF1-059, Mecklenburg County
Solar + storage
99.2 MWWithdrawn / abandoned Mecklenburg, VAPJM Jul 2019target 2021
Solar project AE2-196, Wythe County
Solar
94.6 MWWithdrawn / abandoned Wythe, VAPJM Mar 2019target 2022
Solar project AF2-037, Louisa County
Solar ยท AURA POWER DEVELOPMENTS (USA), LLC
94.0 MWWithdrawn / abandoned Louisa, VAPJM Nov 2019target 2021
Solar project AE2-233, Accomack County
Solar
94.0 MWWithdrawn / abandoned Accomack, VAPJM Mar 2019target 2022
Solar project AF1-031, Caroline County
Solar
93.5 MWWithdrawn / abandoned Caroline, VAPJM May 2019target 2022
Solar project AE2-250, Greensville County
Solar ยท Wyatt Mill Solar, LLC
82.5 MWWithdrawn / abandoned Greensville, VAPJM Mar 2019target 2021
Battery storage project AF2-040, Fauquier County
Battery storage
75.0 MWWithdrawn / abandoned Fauquier, VAPJM Dec 2019target 2023
Battery storage project AF1-266, Dinwiddie County
Battery storage ยท Invenergy Solar Project Development LLC
74.5 MWWithdrawn / abandoned Dinwiddie, VAPJM Sep 2019target 2022
Skyline Solar
Solar
73.0 MWWithdrawn / abandoned Rockingham, VAPJM Aug 2019target 2024
Anna River Solar
Solar ยท Anna River Solar, LLC
72.0 MWWithdrawn / abandoned Hanover, VAPJM Nov 2019target 2023
Alameda Solar
Solar
70.0 MWWithdrawn / abandoned Fauquier, VAPJM Mar 2019target 2027
Solar project AF1-074, Sussex County
Solar
68.0 MWWithdrawn / abandoned Sussex, VAPJM Jul 2019target 2022
Solar project AF2-036, Richmond County
Solar
62.0 MWWithdrawn / abandoned Richmond, VAPJM Nov 2019target 2023
Solar project AF1-115, Surry County
Solar
60.0 MWWithdrawn / abandoned Surry, VAPJM Sep 2019target 2021
Solar project AE2-186, Fauquier County
Solar
60.0 MWWithdrawn / abandoned Fauquier, VAPJM Mar 2019target 2020
Shockoe Solar Farm
Solar ยท Zenith Solar, LLC
60.0 MWWithdrawn / abandoned Pittsylvania, VAPJM Mar 2019target 2020
Solar project AF2-049, Caroline County
Solar
60.0 MWWithdrawn / abandoned Caroline, VAPJM Dec 2019target 2021
Solar project AF1-323, Albemarle County
Solar ยท Vista Energy Facility, LLC
55.0 MWWithdrawn / abandoned Albemarle, VAPJM Sep 2019target 2022
Solar + storage project AF1-067, Caroline County
Solar + storage
50.0 MWWithdrawn / abandoned Caroline, VAPJM Aug 2019target 2022
Battery storage project AF1-066, Loudoun County
Battery storage
50.0 MWWithdrawn / abandoned Loudoun, VAPJM Aug 2019target 2021
Solar project AF1-079, Louisa County
Solar
44.8 MWWithdrawn / abandoned Louisa, VAPJM Aug 2019target 2021
Solar project AE2-231, Caroline County
Solar
44.0 MWWithdrawn / abandoned Caroline, VAPJM Mar 2019target 2022
Battery storage project AE2-188, Culpeper County
Battery storage
40.0 MWWithdrawn / abandoned Culpeper, VAPJM Mar 2019target 2020
Surry Solar Center
Solar
20.0 MWWithdrawn / abandoned Surry, VAPJM May 2019target 2023
Mantura II
Solar
20.0 MWWithdrawn / abandoned Surry, VAPJM Feb 2019target 2022
Bradley BridgeSolar
Solar
20.0 MWWithdrawn / abandoned Chesterfield, VAPJM Mar 2019target 2025
Hosier Road Solar
Solar
20.0 MWWithdrawn / abandoned City Of Suffolk, VAPJM Mar 2019target 2022
Bradley Ridge Solar
Solar
20.0 MWWithdrawn / abandoned Chesterfield, VAPJM Mar 2019target 2025
Solar project AE2-108, Hanover County
Solar
20.0 MWWithdrawn / abandoned Hanover, VAPJM Feb 2019target 2020
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)